Successful go-live of mFRR capacity market in Denmark
An important milestone in the NBM-program was reached on 20 June 2023 when the Danish TSO Energinet had a successful national go-live of their mFRR capacity market. About capacity market …
New Market Handbook for aFRR and mFRR capacity markets
The Market Handbook for aFRR capacity market has been updated to also cover the mFRR capacity market. Both aFRR and mFRR capacity markets are handled in the same Nordic platform, …
Rethinking the method for a Nordic capacity market for mFRR
A proposed Nordic method for a common capacity market for manual frequency restoration reserves (mFRR) has been withdrawn. The reason is that the Nordic TSOs were notified that the Nordic …
Target is set for mFRR capacity markets
Following the launch of the Nordic aFRR capacity market in December 2022, the NBM program has revised the plans for the implementation of the national mFRR capacity markets. The target …
Presentation and link to recorded NBM webinar on the Public consultation for proposal for Nordic mFRR Capacity Market methodologies
Thank you for participating in the webinar on Nordic TSOs proposal for Nordic mFRR Capacity Market methodologies on 11. August 2022. The methodologies are out for public consultation until 22. …
Invitation to national webinars for walkthrough of BSP implementation guide for mFRR capacity market, 22-24 June 2022
NBM is pleased to welcome Norwegian, Swedish and Danish BSPs* to webinars for an introduction of the mFRR capacity market BSP implementation guide. On the way towards a Nordic mFRR …