Updated NBM roadmap
The NBM roadmap has been updated so that it mirrors updates in the project milestones. The updates concerns the following milestones: Go live date for Flowbased is October 29 2024 …
The NBM roadmap has been updated so that it mirrors updates in the project milestones. The updates concerns the following milestones: Go live date for Flowbased is October 29 2024 …
The Nordic steering group for 15 MTU & IDA has decided that the 15-minute MTU in the Intraday market will not be implemented in January as originally planned. Instead, March …
Automated Nordic mFRR EAM will go live on December 3rd, 2024, at 13:00 CET. During today’s NBM Roadmap Webinar (September 27th), the go-live timeslot for the Nordic mFRR EAM was …
NBM is pleased to invite market participants to a Nordic webinar October 7, where key insights and raw data from test runs of the mFRR shadow operation will be presented. …
The NBM program is pleased to invite you to the upcoming Nordic Balancing Model Roadmap Webinar that aims to provide e a comprehensive overview of the upcoming go-lives. The webinar …
Please find the latest versions of the implementation guides for aFRR and mFRR capacity markets and relevant example files, as well as the latest version of the implementation guide for …
The updated memo provides an outlook for the mFRR standard product development up until connection to the European platform for mFRR energy activation, MARI (Manually Activated Reserves Initiative), and describes …
As previously announced, the Nordic mFRR energy activation market will go live on Tuesday, December 3, 2024. In this regard, Energinet would like to invite you to a planning meeting …
The main goal of these BSP-meetings is so that actors working towards participating in mFRR EAM from go-live should have the opportunity to discuss relevant issues related to this work, …
The aFRR energy market was taken in operation in Finland on June 12th at 14.25 pm (EET). The energy market enables aFRR energy bids near real time and optimizes aFRR …
The Nordic TSOs have completed the Evaluation Report for the Nordic aFRR capacity market covering analysis for the year 2023. The Evaluation Report covers the mandatory evaluation criteria set out …
– Updated go-live date – Product characteristics for the market – Bid message size limit increased – Description of resending of BidAvailability document and ReserveAllocationResult document – Codes for Disturbance …
The Nordic TSOs are hereby sending methodologies for a trilateral mFRR capacity market between Denmark, Finland and Sweden in public consultation. The consultation material consists of: Explanatory document to …
The Nordic TSOs are hereby sending amendments to methodologies for the Nordic aFRR capacity market in public consultation. The consultation material consists of: Explanatory document to amendments for methodologies …
Energinet has previously announced that we expected to join the European aFRR platform, PICASSO, on 28 May 2024. Energinet regrets to announce that the Danish connection has been delayed until …
As communicated earlier, the original plan for the start of a Norwegian mFRR capacity market was 10 December of this year. However, after completing the final testing phase in late …
Version 1.1.4 of the “Implementation guide mFRR Energy Activation Market – BSP” is now published. Implementation-Guide-mFRR-energy-activation-market-BSP-v114 The guide is now more strictly focused on the mFRR EAM market interface from …
The go-live date of Nordic mFRR EAM has now been set to 3 December 2024. Consequently, the Nordic TSOs will now intensify cooperation with market participants to prepare to put …
The go-live of the Norwegian mFRR capacity market is moved from 10 December 2023, to the first quarter of 2024. The existing Norwegian capacity market for RKOM will continue as …